N.C. Gen. Stat. § 44A-12(c) – Statutory form of Claim of Lien
on Property.
N.C. Gen. Stat. § 44A-12(d) – A Claim of Lien on Property
may not be amended; it must be cancelled, and a new lien
substituted within 120-day ling timeframe.
N.C. Gen. Stat. § 44A-13 – Lawsuit to enforce Claim of Lien
on Property; required to be brought within 180 days of last
furnishing.
N.C. Gen. Stat. § 44A-18 – Claims of Lien on Funds available
to subcontractors.
N.C. Gen. Stat. § 44A-18(d) – Subrogation rights do not extend
to subcontractors and suppliers more remote than third-tier.
N.C. Gen. Stat. § 44A-19 – Statutory form of Claim of Lien
on Funds.
N.C. Gen. Stat. § 44A-35 – Attorneys’ fees available for
prevailing party at discretion of court when there is an
unreasonable refusal by losing party to resolve the matter.
I. PRELIMINARY QUESTIONS:
Was the construction project private or public?
A contractor on a private project is entitled to a
Mechanic’s lien against the property under Chapter 44A.
Conversely, as public property is owned by the people
of the public, public construction projects cannot be
liened or foreclosed. When construction related work
is contracted to be performed on government-owned
property (such as for the construction of a school, work
on a stormwater management system, or building a new
road) there will most often be a surety “payment” bond
covering the project. A Contractor who has not been paid
for its work on a public project can assert a claim against
the payment bond for payment of amounts owed.
Who is your client?
In NC there are two types of mechanic’s liens, Liens
on Real Property for parties contracting directly with
the Owner (See N.C.G.S. § 44A-7 – 44A-16); and Liens
on Funds for parties contracting with a party other than
the Owner, such as a Subcontractor or Supplier (See
N.C.G.S. § 44A-18 — 44A-23)
A subcontractor may also claim a Lien on Property in
addition to the Lien on Funds in certain circumstances
via subrogation, or also in instances when the Owner
made improper payments to its Contractor in violation
of a valid Lien on Funds after receiving notice. If your
client is a subcontractor or supplier, its lien on property
claim will be asserted via “subrogation” by “stepping
into the shoes” of the higher-tier contractor to assert
the rights that contractor has against the Owner for any
amounts due. This means that whenever an owner has
already paid the general contractor, a subcontractor
will not have lien rights.
When did your client perform the work?
While Claims of Liens on Property are a powerful
statutory tool for collecting payment, they accordingly
have some substantial limitations and procedural
requirements. Perhaps the most common invalidating
factor is conformity with the 120-day ling period.
N.C.G.S. § 44A-12(b) requires that all claims of lien
must be led “not later than 120 days after the last
furnishing of labor or materials at the site…” This short
time-ling deadline often sneaks up on many clients
as 120 days is very brief considering the time between
when the work is performed and when a potential lien
claimant realizes there is a real problem getting paid.
Claims of Lien on Funds of subcontractors do not have
the same 120-ling deadlines. Rather, a Lien on Funds
is limited to the statute of limitations and statute of
repose on the underlying breach of contract claim. A
lien claimant may also extend the deadline for ling an
action to enforce a Lien by tolling agreement (Charlotte
Motor Speedway, Inc. v. Tindall Corp., 672 S.E.2d 691,
694 (N.C. Ct. App. 2009.)
What Pre-Lien Notices were posted for the project?
a. Lien Agent
For any contract for construction work over $30,000
and which is not for the improvement of, or an
addition of an accessory building or structure to, a
single-family, Owner-occupied residence, a “Lien
Agent” must be appointed by the Owner or its
representative. The Lien Agent is an authorized
title insurance company appointed to receive and
track notices from contractors and subcontractors
of potential claims of lien.Contractors and
Subcontractors are required to serve a Notice to Lien
Agent upon the Lien Agent designated on a project
within 15 days of rst furnishing labor, materials,
services or equipment. The NC Online Lien Agent
System website, www.liensnc.com, allows potential
lien claimants to easily le and serve notice on the
lien agent electronically. The Notice preserves the
right of a potential lien claimant to pursue a Claim
of Lien against the project property later. However,
failure to le and serve a Notice to Lien Agent will
only preclude a lien claim if the property is sold,
renanced, or otherwise transferred prior to Notice
being given. The Notice to Lien Agent does not get
led with the Clerk of Superior Court.
b. Notice of Contract / Notice of Subcontract
An Owner or Contractor is also required to le with
the Clerk of Court and post at the project property
a Notice of Contract within 30 days of the later
of: (i) the date a building permit is issued for the
improvement; or (ii) the date the Contractor is
a.
c.
d.
b.