Record (WPQR) shall serve as
written verification and shall list
all of the essential variables of
Table 4.10” (AWS D1.1-98, para.
4.21).
Another situation is that the
erector may have the qualifica-
tion records, but the results of
mechanical, visual and NDT are
not listed. Without test results,
the qualification may be suspect.
To make the qualification credi-
ble, this information must be
recorded and retained. As a
matter of reference, the D1.1
Code has an example WPQR
form in Annex E with space
included for the visual, destruc-
tive and radiographic test results
(AWS D1.1-98, pg. 305).
Additionally, the date and an
authorized signature must be on
the WPQR. The Code says that
the welder’s qualification “shall
be considered as remaining in
effect indefinitely unless ... the
welder is not engaged in a given
process of welding for which the
welder ... is qualified for a period
exceeding six months...” (AWS
D1.1-98, para. 4.2.3.1). This
means that as long as the welder
welds with the process for which
he is qualified at least once every
six months, his qualification last
forever unless there is reason to
question his ability. The key to
this requirement is that the date
must be recorded on the WPQR
form when the welder was first
qualified. Also, a log must be
kept to verify that the welder
remains current in his qualifica-
tion.
To make record keeping easi-
er, many erectors use commer-
cially available computer soft-
ware packages to track welder
qualification.
• Are welders qualified per
the project requirements
(i.e., AWS, AASHTO,
ASME)? (AISC, Op34)
“Some welders were welding
with FCAW but were only quali-
fied for SMAW.”
The problem here is that the
welder qualification provisions of
AWS D1.1 have been violated.
The Code states that “changes
beyond the limitation of essen-
tial variables for welders...
shown in Table 4.10 shall
require requalification” (AWS
D1.1-98, para. 4.22). The weld-
ing process (e.g., FCAW, SMAW,
GMAW and GTAW) used during
qualification is the first essential
variable listed in Table 4.10 of
the Code. This table states that
if the welder is going to change
to a process for which he is not
qualified, he must qualify for
that process as well.
Other essential variables are
SMAW F-number, non-approved
electrodes/shielding medium in
the AWS A5 filler metal specifi-
cations, position, material thick-
ness, vertical progression, omis-
sion of backing and number of
electrodes (AWS D1.1-98, Table
4.10).
O
THER WELDING P
ROBLEMS
• In the event the applicant
purchases weld wire, steel
material, paint, castings,
etc., are the manufactur-
er’s test reports or certifi-
cates of compliance on file
at the location where the
material is being utilized?
(AISC, Advanced Program
Only — Op40))
“No welding electrode
Certificates of Conformance were
on file.”
The welding consumables (i.e.,
electrode, electrode/flux combi-
nation, or electrode/shielding
gas) used on the job site must
conform to the provisions of the
appropriate AWS A5 filler metal
specifications. Filler metal tests
of conformance are conducted by
the welding consumable manu-
facturer. The results of these
tests are reported on a certificate
of conformance. Copies of the
certificates of conformance must
be kept at the job site for each
consumable used for the
Advanced Certification Program.
The Bridge Code requires that
the filler metal tests of confor-
mance be conducted every year
(AWS D1.5-96, para. 5.5), and
the erector must maintain copies
of the most current certificates.
The Structural Code states that
“when requested by the
Engineer, the contractor or fabri-
cator shall furnish certification
that the electrode or electrode-
flux combination will meet the
requirements of the classifica-
tion” (AWS D1.1-98, para.
5.3.1.1). AWS A5.01-87 Filler
Metal Procurement Guidelines
have several schedules that per-
mit re-certification of electrodes
to different time periods. For
example, Schedule G calls for re-
certification on an annual basis,
while Schedule F allows for the
use of the manufacturer’s stan-
dard testing levels. Some manu-
facturers use a three year period
for products unlikely to be used
on bridge projects where D1.5
requires annual re-certification.
• Are flux and rod ovens
adequate and close enough
to where the work is being
performed and are they
operating per the latest
AWS requirements? (AISC,
Op36)
“Rod ovens on site, but the
temperature inside the oven was
only 100 degrees F.”
Electrode storage ovens must
be available on site, the tempera-
ture inside the oven must be
maintained to at least 250
degrees F, and the oven must be
reasonably close to where the
welding is actually done. The
D1.1 Code requires that “imme-
diately after opening the hermet-
ically sealed container, elec-
trodes shall be stored in ovens
held at a temperature of at least
250 degrees F (120 degrees C)”
(AWS D1.1-98, para. 5.3.2.1).
Problems can arise if the con-
sumables are not properly main-
tained. For example, when weld-
ing a higher strength steel,
delayed cracking can occur even
with low hydrogen electrodes if
they are not stored and handled
properly. Major rework may
result, and cracking is a poten-