T
HE
AISC ERECTOR C
ERTIFICATION
PROGRAM HAS BEEN ESTABLISHED TO
ENHANCE THE QUALITY OF STRUCTUR
-
AL STEEL ERECTION
. Contractors are cer-
tified based on their demonstrated expe-
rience, capability and awareness of
sound erection practices. Included in
the program are certain welding
requirements. These provisions are not
new and, in most cases, have been code
requirements for many years; however,
some additional documentation may be
imposed. Any contractor doing work in
accordance with AWS D1.1 or D1.5 is
already required to comply with these
code provisions.
The Structural Welding Code is a
“consensus document that represents
the collective wisdom of designers, fabri-
cators, inspectors, educators and consul-
tants, acquired over decades of experi-
ence” (Post, J.W., "Welding Solutions:
Put Things in Perspective with the AWS
D1.1 Code” 1998 National Steel
Construction Conference Proceedings).
It is not just a book of rules; rather it is
a document that promotes quality work.
The erector certification program
focuses on quality and safety, both of
which are key to the success of a project
and directly influence the cost effective-
ness of steel erection. Now is the time
for all erectors to get on board and join
the ranks of certified erectors. In a
learning curve analogous to that experi-
enced by certified building and bridge
fabricators more than 20 years ago,
steel erectors will also need to expand
their comfort zone as they embrace this
program. Eventually, it is expected that
the program will be end-user driven
through contract specifications. The
Modern Steel Construction / May 1999
goals of the program are to increase
awareness of quality and safety issues
in erector organizations and to provided
an incentive to comply with quality
requirements. A commitment from
management to become a certified erec-
tor in ‘99 will prove to be a wise deci-
sion.
The authors hope to provide some
helpful insight into the welding require-
ments associated with the AISC Erector
Certification Program, as well as some
of the code requirements. This paper is
not intended to be comprehensive, but
will address several key issues. A thor-
ough review of the AISC Erector
Certification Program and applicable
codes is recommended.
In the realm of steel erection, there are
several misconceptions related to weld-
ing requirements. To obtain certifica-
tion, erectors must first move beyond the
following fallacies and address the root
problems in the industry.
Misconception #1:
The AWS D1.1 Structural Welding
Code applies to shop fabrication
only.
The D1.1 Code specifically states that
“this code contains the requirements
for fabricating and erecting welded
steel structures” (emphasis added,
AWS D1.1-98, para. 1.1). The Code
contains provisions, such as joint tol-
erances and fitup (AWS D1.1-98, para
WHAT EVERY STEEL
ERECTOR SHOULD KNOW
ABOUT WELDING
REQUIREMENTS
(BEFORE THE A
UDITORS A
RRIVE)
Duane K. Miller
(top) is Manager of
Engineering
Services and R.
Scott Funderburk is
Welding Design
Engineer with The
Lincoln Electric
Company in
Cleveland.
Common Misconceptions
5.22), that must be followed regard-
less of where the welding is done. In
fact, many of the sections were writ-
ten with field erection in mind. For
example, if the root opening on a
groove weld exceeds the “as-fit” toler-
ances, the Code provides options for
resolution of this problem (AWS
D1.1-98, para. 5.22.4.3 and 5.22.4.4).
It is speculated that these provisions
are used more frequently in the field
than in the shop.
The D1.1 Code is equally applicable
to both shop fabrication and field con-
struction.
Misconception #2:
If a prequalified welding proce-
dure is used, then a written WPS
is not required.
The D1.1 Code mandates that “all
prequalified WPSs shall be written”
(D1.1-98, para. 3.1). Welding
Procedure Specifications are the com-
munication tool that gives the welder
instructions on how to make the
weld. Items such as minimum pre-
heat temperature, maximum inter-
pass temperature and bead place-
ment are listed on the WPS and must
be maintained to obtain the required
weld soundness and mechanical prop-
erties. More information on WPS
development is included in in
"Reviewing and Approving Welding
Procedure Specifications" (Miller and
Funderburk, NSCC 1998) and "What
Every Engineer Needs to Know About
Welding Procedures" (Miller, NSCC
1997).
Written WPSs are required for all
welding, including prequalified proce-
dures.
Misconception #3:
Quality Assurance will handle all
of the field inspection issues – the
contractor does not need to do
any inspection.
Both the AWS D1.1 and D1.5 Codes
specifically define inspection respon-
sibilities for the contractor. D1.1
names the “Fabrication/Erection
Inspector” as the designated person
who acts on behalf of the contractor
with regard to all inspection and
quality matters (AWS D1.1-98, para.
6.1.3.1). D1.1 also says that fabrica-
tion/erection inspection “shall be per-
formed as necessary prior to assem-
bly, during assembly, during welding,
and after welding to ensure that
material and workmanship meet the
requirements of the contract docu-
ments. Fabrication/erection inspec-
tion and testing are the responsibili-
ties of the contractor unless
otherwise provided in the contract
documents”(AWS D1.1-98, para.
6.1.2.1). AWS D1.5 mandates that
the Quality Control (QC) function is
the responsibility of the erector (AWS
D1.5-96, para. 6.1.1.1), and the QC
Inspector works on behalf of the erec-
tor for inspection, testing and quality
matters (AWS D1.5-96, para. 6.1.2.1).
For many field projects, the contract
will require Verification or Quality
Assurance (QA) Inspection, often
stipulating that NDT be performed
by the Verification Inspector (AWS
D1.1-98, 6.1.2.2). This does not, how-
ever, preclude or replace the QC
Inspection that is required by the
Code. For more information on this
issue, the authors recommend
“Ensuring Weld Quality in Structural
Applications: The Roles of Engineers,
Fabricators and Inspectors (Part I of
III)” (Miller, NASCC 1996).
The contractor is responsible for erec-
tion inspection and testing, unless
specifically exempted by the contract
documents.
Misconception #4:
The union hall takes care of all
the welder qualification issues.
Indeed, unions do provide a valuable
service to the industry through their
welder training and testing pro-
grams. Welders can even become cer-
tified welders through the AWS
Welder Certification Program.
However, in terms of the AWS D1.1
Code, it is the contractor’s responsi-
bility to qualify all welders, welding
operators, stud welders and tack
welders (AWS D1.1-98, para. 4.1.2.2
and 7.7.4). If a welder was qualified
on a previous job, that performance
qualification may be acceptable pro-
vided that proper documentation and
evidence has been maintained and
that the Engineer, not the contractor,
approves it (AWS D1.1-98, para.
4.1.2.1).
Welder qualification is the contrac-
tor’s responsibility.
Modern Steel Construction / May 1999
The authors would
like to thank Tom
Schlafly of AISC,
Inc. and Farnham
Jarrard, Clare
Ulstad and Art
Arndt of the Quality
Auditing Company,
Inc. for their valu-
able input on this
paper, as well as for
their diligent contri-
butions to the
structural steel
industry for many
years.
To improve quality and safety,
it is important that these mis-
conceptions be exposed and cor-
rected. These misunderstand-
ings can lead to other problems,
such as those discussed below, if
they are not addressed.
The acceptance criteria of the
audit are categorized in three
areas: Application (Ap),
Management (Mg) and
Operations (Op). These criteria
have requirements related to all
aspects of steel erection, includ-
ing welding. Based on results
from initial audits, nonconfor-
mance has been found in the fol-
lowing: Welding Procedure
Specifications, quality control,
welder qualification and other
miscellaneous welding issues.
To aid the erector in the certifi-
cation process, each “problem
item” is quoted from the AISC
Certified Advanced Steel Erector
Evaluation Checklist with exam-
ples of auditor citations of specif-
ic requirements. A few of the
requirements are for “Advanced”
Certification only, and these are
noted in the applicable sections
below.
WELDING PROCEDURE
SPECIFICATIONS
Are representative weld
procedures submitted?
(AISC, Ap10)
“Erector did not submit any
WPSs.”
The contractor must have
WPSs that cover every weld to
be made on the job, and the erec-
tor must submit several to the
auditors for review. Also, an
inspector or the Engineer could
ask to review the WPSs at any
time (AWS D1.1-98, para. 4.1.1,
4.2.3 and 6.3.1). Therefore,
WPSs should be kept current, in
Modern Steel Construction / May 1999
use by the welders and ready for
submission. It also makes good
business sense, because complete
and proper WPSs generally
encourage quality and productiv-
ity.
“No steel specification or grade
was listed on the WPS.”
In this case, the WPS was sub-
mitted, but it was incomplete.
One of the essential variables is
the base metal specification and
grade (AWS D1.1-98, para.
4.7.3); this information must be
explicitly stated on the WPS.
Other examples of incomplete
or incorrect WPSs are the follow-
ing: polarity not listed, no date
shown, backing to be used with-
out the backing material desig-
nated, no supporting PQRs for
qualified procedures, and pre-
qualified status declared with a
non-prequalified process (e.g.,
GMAW short circuiting).
· Are approved written
welding procedures in
close proximity to and
used by the welders?
(AISC, Advanced Program
Only — Op444)
“The WPS was for E7018, and
the welder was using E71T-8.”
In this example, either the
welder had the wrong WPS or he
was violating the WPS he was
using. Whichever was the case,
what the welder was doing did
not match the requirements of
the WPS. The auditors will
often verify that the actual weld-
ing is in conformance with the
WPS.
“The WPSs were not at the job
site — apparently they are kept
at the home office.”
The home office is not “in close
proximity” to the welder. One of
the key objectives for WPSs is to
clearly communicate the require-
ments to the welder and inspec-
tors. This can not effectively
take place with the instructions
filed away at the office. The
Code does not say that the
welder must keep the WPS with
him at all times. However, the
welder should have quick access
to it. On most job sites, the field
office trailer is an adequate loca-
tion for storage of the WPSs. On
some projects, however, the trail-
er may be too far away for the
welding crew to readily retrieve
the documents. In this case, it
may be more appropriate to
issue a set of WPSs to each crew.
The WPS is intended to control
the welding. To do the work
properly, the welders need the
information recorded on the
WPS, including the allowable
tolerances.
“The WPS listed 225 degree F
minimum preheat temperature,
and the welder was using a 150
degree F crayon.”
The WPS must be properly
followed, and the welder must
use the right tools (the correct
temperature indicating crayon in
this case). Here, the welder does
not know if the steel is above the
minimum specified preheat tem-
perature of 225 degree F. He
only knows if it is above 150
degree F, and he can not main-
tain the minimum specified pre-
heat temperature.
Several other things could
happen if the WPS is not fol-
lowed, including: improper weld
size, maximum interpass tem-
perature exceeded, wrong elec-
trode, incorrect travel speed, and
other problems. The result could
be inadequate structural perfor-
mance, hydrogen cracking,
lamellar tearing, increased cost,
timely repairs and schedule
over-runs.
“The welder was running on
the wrong polarity and did not
know the difference between DC
positive and negative.”
The auditors expect the
welder to understand the funda-
mental issues covered by the
WPS, including electrode polari-
ty. The welder should also have
a basic understanding, for exam-
Specific Audit
Problems
ple, of welding processes (e.g.,
FCAW vs. SMAW), visual accep-
tance criteria, joint and weld
types (e.g., butt joint with a sin-
gle-bevel groove weld), joint fit-
up tolerances, and position (e.g.,
2F and 6G).
QUALITY C
ONTROL
If welding is required, is a
competent welding techni-
cian (such as a CWI or
ACWI) employed by the
applicant? (AISC,
Advanced Program Only —
Mg166)
“Erector had no welding
inspector.”
It is important to have person-
nel available to the job site who
have training in welding, includ-
ing the AWS D1 Welding Codes,
welding processes, inspection
technology and quality accep-
tance criteria. The Certified
Welding Inspector (CWI) pro-
gram sponsored by AWS
requires the participants to
demonstrate their knowledge of
these issues through job experi-
ence and examination. Having a
CWI on staff is no guarantee
against problems, but it does
provide some level of confidence
when trouble arises. The D1.1
Code does not require a AWS
CWI; there are other acceptable
qualification bases such as the
Canadian Welding Bureau CWI
(AWS D1.1-98, para. 6.1.4.1).
Since quality is a core objective
of the AISC Erector Certification
Program, incorporating qualified
people is fundamental. A CWI is
not essential to obtaining a cer-
tificate but there must be some-
one available who has demon-
strated awareness of welding
and code issues.
Are job site superinten-
dents and foremen conver-
sant with current work-
manship requirements
such as those contained in
AWS, AREA, AISC,
AASHTO, specifications?
Modern Steel Construction / May 1999
(AISC, Op17)
“The welding foreman did not
know what the AWS D1.1 Code
was.”
No one expects the job super-
intendent or the foreman to
know all the applicable code pro-
visions from memory, but they
should at least know what the
code is and where to find
answers to common code ques-
tions. For example, the auditor
may ask the foreman to show
him the code provisions for
allowable porosity levels. The
foreman should be able to fairly
quickly open the AWS D1.1 Code
and turn to Chapter 6 -
Inspection to find the answer.
Has a key person been
assigned the responsibility
of bolting or welding joints
in accordance with the
applicable specifications?
(AISC, Op30)
“No one knew who was in
charge of welding.”
At the heart of this require-
ment are two issues: responsi-
bility and specifications. To
achieve high quality, key people
must ensure that the work con-
forms to the standards estab-
lished in the specifications (e.g.,
AWS D1.1 and contract docu-
ments). Along with responsibili-
ty must come the motivation to
do the right thing and to see
things through to completion.
Responsibility also encourages
pride of workmanship, owner-
ship, the understanding that it
has to be done correctly and that
it is up to the individual to
accomplish the goal. This person
can be the one responsible for
assuring quality of the work, but
he must know the criteria and be
active on the site. If this respon-
sibility is not given to one specif-
ic person, the likelihood of con-
formance to the workmanship
standards in the specifications is
low. The person in charge of
welding must also have the
authority to make decisions.
There is little benefit in giving
responsibility to someone who
can not authorize the work to be
done.
Do the welders under-
stand, comply with, and
check their welds against
the workmanship and
technique requirements of
AISC, AASHTO, or AWS?
(AISC, Op35)
“The welder was making welds
with unacceptable undercut and
didn’t know what was wrong.”
The Code says that, “the con-
tractor shall be responsible for
visual inspection and necessary
correction of all deficiencies in
materials and workmanship in
accordance with the require-
ments of this code” (AWS D1.1-
98, para. 6.6.1). This includes
the following issues: cracks,
weld/base metal fusion, craters,
weld profiles, weld size, under-
cut, and porosity (AWS D1.1-98,
Table 6.1). This code provision
establishes the basis for the
requirement that the welders
must “understand, comply with,
and check” their work.
According to the auditor’s note
in this example, the welder
apparently didn’t know what
undercut was, or that there were
unacceptable limits. Since the
contractor is responsible for visu-
al inspection, having the welders
check to make sure that their
work meets the visual inspection
criteria is an effective first step.
WELDER QUALIFICATION
Does the applicant have a
record of the craft workers
who are certified welders?
(AISC, Mg7c)
“No Welder Performance
Qualification Records (WPQRs)
were available.”
In this example, records were
inadequate to prove the qualifi-
cation of the welders. AWS D1.1
states that “the Welding
Performance Qualification
Record (WPQR) shall serve as
written verification and shall list
all of the essential variables of
Table 4.10” (AWS D1.1-98, para.
4.21).
Another situation is that the
erector may have the qualifica-
tion records, but the results of
mechanical, visual and NDT are
not listed. Without test results,
the qualification may be suspect.
To make the qualification credi-
ble, this information must be
recorded and retained. As a
matter of reference, the D1.1
Code has an example WPQR
form in Annex E with space
included for the visual, destruc-
tive and radiographic test results
(AWS D1.1-98, pg. 305).
Additionally, the date and an
authorized signature must be on
the WPQR. The Code says that
the welder’s qualification “shall
be considered as remaining in
effect indefinitely unless ... the
welder is not engaged in a given
process of welding for which the
welder ... is qualified for a period
exceeding six months...” (AWS
D1.1-98, para. 4.2.3.1). This
means that as long as the welder
welds with the process for which
he is qualified at least once every
six months, his qualification last
forever unless there is reason to
question his ability. The key to
this requirement is that the date
must be recorded on the WPQR
form when the welder was first
qualified. Also, a log must be
kept to verify that the welder
remains current in his qualifica-
tion.
To make record keeping easi-
er, many erectors use commer-
cially available computer soft-
ware packages to track welder
qualification.
Are welders qualified per
the project requirements
(i.e., AWS, AASHTO,
ASME)? (AISC, Op34)
“Some welders were welding
with FCAW but were only quali-
fied for SMAW.”
The problem here is that the
welder qualification provisions of
AWS D1.1 have been violated.
The Code states that “changes
beyond the limitation of essen-
tial variables for welders...
shown in Table 4.10 shall
require requalification” (AWS
D1.1-98, para. 4.22). The weld-
ing process (e.g., FCAW, SMAW,
GMAW and GTAW) used during
qualification is the first essential
variable listed in Table 4.10 of
the Code. This table states that
if the welder is going to change
to a process for which he is not
qualified, he must qualify for
that process as well.
Other essential variables are
SMAW F-number, non-approved
electrodes/shielding medium in
the AWS A5 filler metal specifi-
cations, position, material thick-
ness, vertical progression, omis-
sion of backing and number of
electrodes (AWS D1.1-98, Table
4.10).
O
THER WELDING P
ROBLEMS
In the event the applicant
purchases weld wire, steel
material, paint, castings,
etc., are the manufactur-
er’s test reports or certifi-
cates of compliance on file
at the location where the
material is being utilized?
(AISC, Advanced Program
Only — Op40))
“No welding electrode
Certificates of Conformance were
on file.”
The welding consumables (i.e.,
electrode, electrode/flux combi-
nation, or electrode/shielding
gas) used on the job site must
conform to the provisions of the
appropriate AWS A5 filler metal
specifications. Filler metal tests
of conformance are conducted by
the welding consumable manu-
facturer. The results of these
tests are reported on a certificate
of conformance. Copies of the
certificates of conformance must
be kept at the job site for each
consumable used for the
Advanced Certification Program.
The Bridge Code requires that
the filler metal tests of confor-
mance be conducted every year
(AWS D1.5-96, para. 5.5), and
the erector must maintain copies
of the most current certificates.
The Structural Code states that
“when requested by the
Engineer, the contractor or fabri-
cator shall furnish certification
that the electrode or electrode-
flux combination will meet the
requirements of the classifica-
tion” (AWS D1.1-98, para.
5.3.1.1). AWS A5.01-87 Filler
Metal Procurement Guidelines
have several schedules that per-
mit re-certification of electrodes
to different time periods. For
example, Schedule G calls for re-
certification on an annual basis,
while Schedule F allows for the
use of the manufacturer’s stan-
dard testing levels. Some manu-
facturers use a three year period
for products unlikely to be used
on bridge projects where D1.5
requires annual re-certification.
• Are flux and rod ovens
adequate and close enough
to where the work is being
performed and are they
operating per the latest
AWS requirements? (AISC,
Op36)
“Rod ovens on site, but the
temperature inside the oven was
only 100 degrees F.”
Electrode storage ovens must
be available on site, the tempera-
ture inside the oven must be
maintained to at least 250
degrees F, and the oven must be
reasonably close to where the
welding is actually done. The
D1.1 Code requires that “imme-
diately after opening the hermet-
ically sealed container, elec-
trodes shall be stored in ovens
held at a temperature of at least
250 degrees F (120 degrees C)”
(AWS D1.1-98, para. 5.3.2.1).
Problems can arise if the con-
sumables are not properly main-
tained. For example, when weld-
ing a higher strength steel,
delayed cracking can occur even
with low hydrogen electrodes if
they are not stored and handled
properly. Major rework may
result, and cracking is a poten-
Modern Steel Construction / May 1999
tial consequence if this require-
ment is not followed. The pur-
pose of the rod oven is to keep
the electrodes dry to help mini-
mize the chances for problems of
this nature. Make sure that the
rod ovens (1) are on the job site,
(2) work properly, and (3) are
close to the location of welding.
SUMMARY
In the form of the D1.1
Structural Welding Code and the
D1.5 Bridge Welding Code, steel
erectors have been given a
readymade two-part “blueprint
for excellence” that will serve
them well in meeting the
requirements of AISC’s Erector
Certification Program.
This paper is part of the 1999
North American Steel
Construction Conference session:
“What Every Steel Erector
Should Know About Welding
Requirements (Before The
Auditors Arrive!).”