finishing requirements or installation requirements that are not standard practice and which impact
pricing, obtaining materials, scheduling, or quality of workmanship.
In some instances, the steel contractor may elect to exclude certain specified elements from the
subcontract workscope. For example, steel contractors will frequently exclude grouting of base
plates. When the steel contractor elects to exclude elements from the workscope, it is important that
the general contractor is aware of these exclusions.
1.8 Steel Fabrication and Erection Subcontracts1.8 Steel Fabrication and Erection Subcontracts
1.8 Steel Fabrication and Erection Subcontracts1.8 Steel Fabrication and Erection Subcontracts
1.8 Steel Fabrication and Erection Subcontracts
Steel construction will usually involve the use of subcontractors and lower tier subcontractors. The
steel contractor may serve as a subcontractor to a general contractor. Specialty contractors, such as
metal deck installers, may serve as lower tier subcontractors to the steel contractor. Typical lower
tier subcontracts found on steel frame projects include: fabrication, erection, metal deck
installation, shear stud installation, metal fabrications, and furnishing of miscellaneous metals.
As with most construction subcontracts, many basic contractual issues need to be addressed.
Typical clauses identifying the date, parties, and contract documents, as well as provisions for
payments, insurance, and dispute resolution etc., should be incorporated. Since this manual is not
intended to be a comprehensive guide to subcontracts, these basic contract components are not
addressed in this manual. The reader should refer to other sources such as AGC650 or AGC655
issued by the Associated General Contractors (AGC) or the A401 issued by the American Institute
of Architects (AIA) for their standard form subcontracts. The purpose of this section is to address
those clauses which are unique or of special interest in steel subcontracts, for both the subcontractor
and the general contractor.
Incorporation by Reference. The subcontract frequently incorporates all or portions of the prime
contract by reference. This has the effect of binding the parties to the conditions of the prime
contract, as if they were physically attached to the subcontract. It is important for both of the
contracting parties to obtain copies of the incorporated documents and to understand their impact.
Occasionally, the terms of the subcontract may conflict with the incorporated terms of the prime
contract. This could be handled by the use of a “precedence” clause (a clause indicating which
document will govern in case of a conflict in documents.)
Scope of Work.Scope of Work.
Scope of Work.Scope of Work.
Scope of Work. The scope of the subcontractor’s work should be clearly defined in the subcontract.
This definition should include the general conditions or services which the subcontractor must
provide, and those which the general contractor will provide for the steel contractor. The general
contractor may use CSI specification sections to indicate work included in the subcontract.
However, care should be taken when describing workscopes that incorporate work from portions of
multiple CSI sections or divisions. For example, the general contractor may require the mason to
furnish steel lintels specified in Division 5 Metals, and installed by the mason under Division 4
Masonry. In this instance, it would be important to indicate clearly to the miscellaneous metals
contractor that lintels were not in the project workscope. Standard workscopes are discussed more
fully in Section 1.9 of this manual.
Use of General Contractor’s EquipmentUse of General Contractor’s Equipment
Use of General Contractor’s EquipmentUse of General Contractor’s Equipment
Use of General Contractor’s Equipment. Under most subcontracts, the subcontractors furnish and
utilizes their own equipment for completing the work. For steel work, there may be rare occasions,
such as in high-rise buildings or on restricted sites, where the general contractor will provide cranes
21